Siting and Curtailment Depth Limit the Grid Headroom Available to New Large Loads
Abstract
Data center demand is increasing faster than generation can be built, encouraging proposals to interconnect large loads on condition that they reduce consumption during high-stress periods. Estimates of how much load can be added via flexibility rest on simplified accounting and report only annual curtailed electricity. Here we use a national energy systems model that co-optimizes hourly generation and load curtailment across 16 U.S. regions to characterize the flexibility and power system impacts of enabling headroom. While 50 GW can be served while curtailing less than 0.1% of its annual energy, small annual curtailment conceals potentially severe operating requirements. Most regions require curtailment deeper than 90% in at least one hour, so the load must disconnect or have sufficient on-site resources to provide full back up. Furthermore, announced data center locations are not aligned with modeled headroom and relying on existing generation fleets raises CO2 emissions and wholesale electricity prices.
Related
- Neutron-star dark-matter limits measure the maximum-mass headroom
- Laser-design methodology for extending an available wavelength range of dual-wavelength injection-seeded laser
- Charmonium production at energies available at the CERN Super Proton Synchrotron and Facility for Antiproton and Ion Research
- Existence of a second phase transition in A-A collisions at energies available at the CERN Large Hadron Collider: A physical interpretation
- Radiation Hardness of Commercially Available NUV-MT Silicon Photomultipliers
BibTeX
@misc{johnson2026siting,
title = {{Siting and Curtailment Depth Limit the Grid Headroom Available to New Large Loads}},
author = {Nils Johnson and Geoff Blanford and John E. T. Bistline},
howpublished = {arXiv},
year = {2026},
month = nov,
doi = {10.48550/arxiv.2611.00462},
eprint = {2611.00462},
archivePrefix = {arXiv},
url = {https://arxiv.org/abs/2611.00462},
}
RIS
TY - UNPB
TI - Siting and Curtailment Depth Limit the Grid Headroom Available to New Large Loads
AU - Nils Johnson
AU - Geoff Blanford
AU - John E. T. Bistline
PY - 2026
DA - 2026/11/01
PB - arXiv
DO - 10.48550/arxiv.2611.00462
UR - https://arxiv.org/abs/2611.00462
AB - Data center demand is increasing faster than generation can be built, encouraging proposals to interconnect large loads on condition that they reduce consumption during high-stress periods. Estimates of how much load can be added via flexibility rest on simplified accounting and report only annual curtailed electricity. Here we use a national energy systems model that co-optimizes hourly generation and load curtailment across 16 U.S. regions to characterize the flexibility and power system impacts of enabling headroom. While 50 GW can be served while curtailing less than 0.1% of its annual energy, small annual curtailment conceals potentially severe operating requirements. Most regions require curtailment deeper than 90% in at least one hour, so the load must disconnect or have sufficient on-site resources to provide full back up. Furthermore, announced data center locations are not aligned with modeled headroom and relying on existing generation fleets raises CO2 emissions and wholesale electricity prices.
ER -