From Product Evidence to Access Rights: Auditing and Routing Non-Firm Grid Connections

Abstract

Non-firm connection products can accelerate grid access while reinforcements are delayed, but their planning value depends on evidence supporting the contractual promise. We develop a one-way evidence-to-access framework for calendarized products. Stage A constructs and fixes directional restriction calendars from public residual-load and day-ahead price-timing signals. Stage B audits the submitted calendar and one bounded common repair, tests joint threshold attainability under the shared annual budget, and applies an aggregation-aware Power Transfer Distribution Factor (PTDF) certificate. Stage C treats the resulting ledger as fixed in queue-aware allocation and intervention planning. In the primary policy-package evaluation, the evidence-supported menu returns the same $2.119$~GW allocation as firm-only access, whereas authorizing the uniformly derated fallback raises awards to $6.442$~GW and reduces backlog from $136.076$ to $113.601$~GW-years; all $4.489$~GW of non-firm awards use the fallback. In a target-free matched control, evidence-routed and state-blind fallback menus attain primary objectives equivalent within EUR~1 and return the same accepted applicants, award years, routes, and intervention portfolio. Thus, in the reported testbed, fallback authorization rather than calendar-specific evidence support drives the access-volume effect.

Related

  1. Learning Choice Model Trees for Feature-Based Multi-Product Pricing: Exact Optimization and Field Evidence
    Jiajie Zhang, Yanqiu Ruan, Xiao Jin +1
    arXivPreprintarXiv licenceFull textOptimisation & controlStatisticsarXiv
  2. Empirical Auditing of Edge-Private Graph Generators
    Anum Fatima, Stratis Limnios, James Adams +4
    arXivPreprintCC BY 4.0Full textStatisticsarXiv
  3. Projective connections on super Heisenberg coinvariants. I
    Giovanni Felder, David Kazhdan, Alexander Polishchuk
    arXivPreprintCC BY 4.0Full textAlgebra & number theoryarXiv
  4. PDECheck: A Diagnostic Software Suite for Auditing Learned PDE Simulators
    Lennon J. Shikhman
    arXivPreprintarXiv licenceFull textNumerical analysis & scientific computingComputational physicsarXiv
  5. GKZ Systems and Gauss-Manin Connections of Families of Projective Hypersurfaces
    Ryo Negishi
    arXivPreprintarXiv licenceFull textAlgebra & number theoryarXiv
BibTeX
@misc{kryeziu2026from,
  title = {{From Product Evidence to Access Rights: Auditing and Routing Non-Firm Grid Connections}},
  author = {Alban Kryeziu and Stuart X. Zhu and Evrim Ursavas},
  howpublished = {arXiv},
  year = {2026},
  month = oct,
  doi = {10.48550/arxiv.2610.15510},
  eprint = {2610.15510},
  archivePrefix = {arXiv},
  url = {https://arxiv.org/abs/2610.15510},
  note = {CC BY 4.0},
}
RIS
TY  - UNPB
TI  - From Product Evidence to Access Rights: Auditing and Routing Non-Firm Grid Connections
AU  - Alban Kryeziu
AU  - Stuart X. Zhu
AU  - Evrim Ursavas
PY  - 2026
DA  - 2026/10/11
PB  - arXiv
DO  - 10.48550/arxiv.2610.15510
UR  - https://arxiv.org/abs/2610.15510
AB  - Non-firm connection products can accelerate grid access while reinforcements are delayed, but their planning value depends on evidence supporting the contractual promise. We develop a one-way evidence-to-access framework for calendarized products. Stage A constructs and fixes directional restriction calendars from public residual-load and day-ahead price-timing signals. Stage B audits the submitted calendar and one bounded common repair, tests joint threshold attainability under the shared annual budget, and applies an aggregation-aware Power Transfer Distribution Factor (PTDF) certificate. Stage C treats the resulting ledger as fixed in queue-aware allocation and intervention planning. In the primary policy-package evaluation, the evidence-supported menu returns the same $2.119$~GW allocation as firm-only access, whereas authorizing the uniformly derated fallback raises awards to $6.442$~GW and reduces backlog from $136.076$ to $113.601$~GW-years; all $4.489$~GW of non-firm awards use the fallback. In a target-free matched control, evidence-routed and state-blind fallback menus attain primary objectives equivalent within EUR~1 and return the same accepted applicants, award years, routes, and intervention portfolio. Thus, in the reported testbed, fallback authorization rather than calendar-specific evidence support drives the access-volume effect.
ER  -