Forecasting and Low-Carbon Demand Response Scheduling of Crane-Group Station-Service Loads for Grid-Friendly Hydropower Station Operation

Abstract

Net power injection at the point of common coupling (PCC) is an important indicator of grid-friendly hydropower operation. High-power station-service equipment may consume regulation margin and cause short-term power disturbances if it is not coordinated with unit dispatch and automatic generation control (AGC) tracking. This paper models hydropower-station crane groups as safety-bounded, forecastable, and dispatchable station-service flexibility resources, and proposes a forecast-embedded low-carbon demand response framework. The framework develops a PCC-coupled station-service model, uses phase-aware probabilistic forecasting to generate crane consumption templates, regeneration templates, and uncertainty intervals, and coordinates rigid, semi-flexible, and flexible crane tasks through rolling mixed-integer optimization to reduce station-service peaks, PCC tracking deviations, and carbon-opportunity costs. A station-oriented digital validation case shows that, while satisfying all task deadlines and safety constraints, the proposed method reduces the representative-day station-service peak by 16.1%, PCC RMSE by 55.1%, and carbon-opportunity cost by 29.7%, and increases regenerative-energy utilization from 54.8% to 86.8%, compared with earliest-start scheduling. An archive replay on an actual hydropower station with a 15.00 MW installed crane fleet then shows that start-time shifting remains available under that station’s work-order windows. On a high-duty maintenance day the representative-day peak falls by 15.4%, and over 20 high- duty days the mean peak falls by 17.3%, while regenerative utilization rises from 65.6% to 90.0%. The two evaluations indicate that crane groups at stations that issue work-order-based crane tasks with usable flexibility windows can be co-scheduled as station-service flexibility resources with phase structure, safety boundaries, and temporal regulation value. The reported magnitudes are those of the two cases and are not claimed for other layouts.

Related

  1. Integrating YOLOv8-based disaster detection with deep reinforcement learning for closed-loop UAV emergency response scheduling: A simulation study
    Chunsheng Zhang, Ruichun He
    PLOS OnePeer-reviewedCC BYFull textNeuroscienceStatisticsPLOSEurope PMCPMC
  2. Design, implementation and validation of a web-based dynamic simulation platform for pumped storage hydropower plant control systems
    Chen Zhang, Ting Liang, Yifan Li +2
    PLOS OnePeer-reviewedCC BY 4.0Full textGeneral mathematicsGeneral physicsPLOS
  3. Online Packet Scheduling with Deadlines and Learning
    Gianmarco Genalti, Achraf Azize, Vianney Perchet
    HALPreprintLicence not statedGeneral mathematicsHAL
  4. Optimal Uniform-like Scheduling of Maintenance
    Yakov Genis, Igor Ushakov
    Reliability: Theory & ApplicationsPeer-reviewedCC BY-NCFull textGeneral mathematicsDOAJ
  5. How natural of a geometric operation is Murasugi sum?
    Thomas Kindred
    arXivPreprintarXiv licenceFull textGeometry & topologyarXiv
BibTeX
@article{wei2026forecasting,
  title = {{Forecasting and Low-Carbon Demand Response Scheduling of Crane-Group Station-Service Loads for Grid-Friendly Hydropower Station Operation}},
  author = {Wanwan Wei and Shangfeng Guo and Xiaolong Cheng and Wanli Dong and Bo Zhang},
  journal = {EAI Endorsed Transactions on Energy Web},
  year = {2026},
  month = oct,
  doi = {10.4108/ew.15670},
  url = {https://doi.org/10.4108/ew.15670},
  note = {CC BY-NC-SA},
}
RIS
TY  - JOUR
TI  - Forecasting and Low-Carbon Demand Response Scheduling of Crane-Group Station-Service Loads for Grid-Friendly Hydropower Station Operation
AU  - Wanwan Wei
AU  - Shangfeng Guo
AU  - Xiaolong Cheng
AU  - Wanli Dong
AU  - Bo Zhang
PY  - 2026
DA  - 2026/10/23
JO  - EAI Endorsed Transactions on Energy Web
DO  - 10.4108/ew.15670
UR  - https://doi.org/10.4108/ew.15670
AB  - Net power injection at the point of common coupling (PCC) is an important indicator of grid-friendly hydropower operation. High-power station-service equipment may consume regulation margin and cause short-term power disturbances if it is not coordinated with unit dispatch and automatic generation control (AGC) tracking. This paper models hydropower-station crane groups as safety-bounded, forecastable, and dispatchable station-service flexibility resources, and proposes a forecast-embedded low-carbon demand response framework. The framework develops a PCC-coupled station-service model, uses phase-aware probabilistic forecasting to generate crane consumption templates, regeneration templates, and uncertainty intervals, and coordinates rigid, semi-flexible, and flexible crane tasks through rolling mixed-integer optimization to reduce station-service peaks, PCC tracking deviations, and carbon-opportunity costs. A station-oriented digital validation case shows that, while satisfying all task deadlines and safety constraints, the proposed method reduces the representative-day station-service peak by 16.1%, PCC RMSE by 55.1%, and carbon-opportunity cost by 29.7%, and increases regenerative-energy utilization from 54.8% to 86.8%, compared with earliest-start scheduling. An archive replay on an actual hydropower station with a 15.00 MW installed crane fleet then shows that start-time shifting remains available under that station’s work-order windows. On a high-duty maintenance day the representative-day peak falls by 15.4%, and over 20 high- duty days the mean peak falls by 17.3%, while regenerative utilization rises from 65.6% to 90.0%. The two evaluations indicate that crane groups at stations that issue work-order-based crane tasks with usable flexibility windows can be co-scheduled as station-service flexibility resources with phase structure, safety boundaries, and temporal regulation value. The reported magnitudes are those of the two cases and are not claimed for other layouts.
SN  - 2032-944X
ER  -