The cost of regulatory delay: quantifying how permitting timelines affect offshore wind energy costs

  1. 1Carnegie Mellon University
  2. 2Instituto Superior Técnico—Universidade de Lisboa
  3. 3Carleton University

Abstract

Rapid deployment of offshore renewable energy and transmission infrastructure can be a major contributor to energy system decarbonization. However, regulatory obligations frequently impose deployment delays that are typically not quantified in cost terms. The costs of such delays should be incorporated in project and technology assessments. Here, a framework is developed that treats the development lag between project inception and operation as a temporal proxy for regulatory and related obligations, and propagates it through a levelized-cost-of-energy calculation to quantify the cost of delay. This framework is used to compare, on a common basis, conventional high-voltage cable transmission with offshore power-to-hydrogen (PtH) alternatives. The framework is applied to three strategies to move energy to shore from offshore wind facilities. The results show that for an example, one gigawatt plant, deploying one year sooner can save €110 million—a relevant metric to gauge the cost of policy designed to expedite deployment. In scenarios where the PtH can be deployed faster than high-voltage cables, the results suggest a limited decision space in which PtH transmission is cheaper, indicating that it will need to realize other benefits to compete with high-voltage cable transmission on cost. Profitability between electricity-based and hydrogen-based transmission is then compared, considering differences in deployment time. There are existing conditions of hydrogen and electricity prices that indicate PtH pathways may be more profitable when a difference in deployment lag is applied. In the example considered here, a lag difference can result in a greater number of exploratory price scenarios where PtH is more profitable. This framework is useful to quantify the implications of regulatory obligations and tune policies to accelerate low-carbon energy deployment.

Related

  1. Diapycnal mixing in submesoscale-permitting simulations of the deep Brazil Basin
    Yonglin Huang, Annalisa Bracco, Kurt Polzin +1
    Ocean SciencePeer-reviewedCC BY 4.0Oceanography & cryosphereCrossref
  2. The role of the oceans for subseasonal prediction: insights from eddy-permitting and eddy-rich coupled forecast systems
    Christopher David Roberts, Sarah Keeley, Kristian Mogensen +2
    arXivPreprintCC BY 4.0Full textAtmospheric science & meteorologyarXiv
  3. Assessment of photovoltaic energy potential over Italy from an ensemble of convection permitting climate models
    Milan Mathew, Giorgia Fosser, Marco Gaetani +17
    Renewable EnergyPeer-reviewedCC BY-NC 4.0Full textAtmospheric science & meteorologyHAL
  4. Benchmarking convection-permitting climate simulations for hydrometeorological characterizations: a comparative study of WRF-SAAG and observation-based products in Chile
    Sofía Segovia-Escafi, Pablo A. Mendoza, Miguel Lagos-Zúñiga +2
    Hydrology and Earth System SciencesPeer-reviewedCC BY 4.0Full textAtmospheric science & meteorologyCrossref
  5. Sensitivity analysis of annual energy production and associated economic losses due to external wake effects on offshore wind clusters: A case study of the Shinan offshore wind cluster in southwest sea of Korea
    Geonhwa Ryu, Dohee Lee, Jungho Kim +4
    PLOS OnePeer-reviewedCC BY 4.0Full textAtmospheric science & meteorologyFluid dynamicsPLOS
BibTeX
@article{santarromana2026cost,
  title = {{The cost of regulatory delay: quantifying how permitting timelines affect offshore wind energy costs}},
  author = {Rudolph Santarromana and Ahmed Abdulla and M Granger Morgan and Joana Mendonça},
  journal = {Environmental Research Letters},
  year = {2026},
  month = oct,
  doi = {10.1088/1748-9326/aea6f2},
  url = {https://iopscience.iop.org/article/10.1088/1748-9326/aea6f2},
  note = {CC BY 4.0},
}
RIS
TY  - JOUR
TI  - The cost of regulatory delay: quantifying how permitting timelines affect offshore wind energy costs
AU  - Rudolph Santarromana
AU  - Ahmed Abdulla
AU  - M Granger Morgan
AU  - Joana Mendonça
PY  - 2026
DA  - 2026/10/08
JO  - Environmental Research Letters
DO  - 10.1088/1748-9326/aea6f2
UR  - https://iopscience.iop.org/article/10.1088/1748-9326/aea6f2
AB  - Rapid deployment of offshore renewable energy and transmission infrastructure can be a major contributor to energy system decarbonization. However, regulatory obligations frequently impose deployment delays that are typically not quantified in cost terms. The costs of such delays should be incorporated in project and technology assessments. Here, a framework is developed that treats the development lag between project inception and operation as a temporal proxy for regulatory and related obligations, and propagates it through a levelized-cost-of-energy calculation to quantify the cost of delay. This framework is used to compare, on a common basis, conventional high-voltage cable transmission with offshore power-to-hydrogen (PtH) alternatives. The framework is applied to three strategies to move energy to shore from offshore wind facilities. The results show that for an example, one gigawatt plant, deploying one year sooner can save €110 million—a relevant metric to gauge the cost of policy designed to expedite deployment. In scenarios where the PtH can be deployed faster than high-voltage cables, the results suggest a limited decision space in which PtH transmission is cheaper, indicating that it will need to realize other benefits to compete with high-voltage cable transmission on cost. Profitability between electricity-based and hydrogen-based transmission is then compared, considering differences in deployment time. There are existing conditions of hydrogen and electricity prices that indicate PtH pathways may be more profitable when a difference in deployment lag is applied. In the example considered here, a lag difference can result in a greater number of exploratory price scenarios where PtH is more profitable. This framework is useful to quantify the implications of regulatory obligations and tune policies to accelerate low-carbon energy deployment.
SN  - 1748-9326
ER  -